Proposes to reroute a portion of an existing 69-kV power line by constructing a power line corridor for approximately 3.5 miles. Includes removing trees from approximately 12.6 acres, clearing trees, drilling 10-foot deep holes to install wooden utility polls 70 feet high, and installing conductor wire. About 3.5 miles of existing power line would be removed from federal and private land.
Description
45 pp. Tables, references, maps.
Township 18 South, Range 11 East, Sections 10, 11, 14, 15 & 22.
Captured May 17, 2007.