North Jetty interim repair finding of no significant impact
Loading...
Date
2008-07-21
Authors
United States. Bureau of Land Management. Coos Bay District
Journal Title
Journal ISSN
Volume Title
Publisher
Abstract
FONSI excludes EIS and Decision Record implements project allowing use of BLM land for an overnight staging area for U.S. Army Corps of Engineers to analyze the environmental effects of an interim repair of the Coos Bay North Jetty. The project will provide a stable entrance channel and minimize the need for maintenance dredging.
Description
6 pp.
BLM has reviewed the EA for the potential effects of the Corps’ use of a 10-acre cleared staging area on the North Spit located about 7 miles north of the jetty on BLM land.
Date of Decision Record is July 22, 2008. Captured September 12, 2008.
Keywords
Public lands -- Oregon -- Coos Bay, Jetties -- Oregon -- Coos Bay -- Maintenance and repair