Forest-wide Documentshttps://scholarsbank.uoregon.edu/xmlui/handle/1794/67972024-03-29T05:32:10Z2024-03-29T05:32:10ZRoad decommissioning for aquatic restoration decision recordMt. Hood National Forest (Agency : U.S.)https://scholarsbank.uoregon.edu/xmlui/handle/1794/87092015-06-18T00:49:41Z2008-12-01T00:00:00ZRoad decommissioning for aquatic restoration decision record
Mt. Hood National Forest (Agency : U.S.)
Analyzes the environmental effects for
decommissioning approximately 84 miles of road across the Forest. Road decommissioning
activities are proposed to improve hydrologic function and aquatic habitat in several high priority
sixth-field subwatersheds. This EA analyzes three alternatives.
13 pp. Tables. Priority areas for watershed and aquatic habitat restoration are within the Fifteenmile Creek, Hood River, and Sandy River basins. Captured March 5, 2009.
2008-12-01T00:00:00ZSite-specific invasive plant treatment for Mt. Hood National Forest and Columbia River Gorge National Scenic Area decision recordMt. Hood National Forest (Agency : U.S.)https://scholarsbank.uoregon.edu/xmlui/handle/1794/87072015-06-18T00:47:15Z2008-03-01T00:00:00ZSite-specific invasive plant treatment for Mt. Hood National Forest and Columbia River Gorge National Scenic Area decision record
Mt. Hood National Forest (Agency : U.S.)
Approves project by the Mt. Hood National Forest (Forest) and Columbia River Gorge National Scenic Area in
Oregon (Scenic Area) initiating invasive plant treatments on 208 sites (approximately
13,000 acres). The purpose of this project is to eradicate, contain and control invasive plant
infestations, to reverse the negative impacts caused by invasive plants, and to restore healthy,
native plant communities and functions at the impacted sites in a cost-effective manner that
meets current management direction. The treatments include: 30 acres of herbicide only
treatment; 50 acres of manual and mechanical treatments; 310 acres of herbicide plus mechanical
treatments; 327 acres of herbicide plus manual treatments; 1510 acres of herbicide plus manual,
mechanical, and cultural; 10,736 acres of herbicide plus manual and mechanical treatments.
Additional acres would be added through an early detection / rapid response strategy (EDRR).
53 pp. Tables, figure, references, appendices, maps. The proposed treatment areas cover
approximately 13,000 acres in Multnomah, Hood River, Wasco, Clackamas, Jefferson, and
Marion counties (See Figure 2-1). This represents 1.1 percent of the National Forest System
lands within the Forest and Scenic Area. Approximately 11,000 acres are located within the
Forest and 2,000 acres within the Scenic Area. The Forest acres are distributed on all four ranger
districts, including 2,444 acres on Barlow Ranger District, 5,596 acres on Hood River Ranger
District; 1,270 acres on Clackamas River Ranger District; and 1,868 acres on the Zigzag Ranger
District. Captured March 5, 2009.
2008-03-01T00:00:00ZRoad decommissioning for aquatic restoration environmental assessmentUnited States. Forest Service. Pacific Northwest Regionhttps://scholarsbank.uoregon.edu/xmlui/handle/1794/87062015-06-18T00:53:45Z2008-01-01T00:00:00ZRoad decommissioning for aquatic restoration environmental assessment
United States. Forest Service. Pacific Northwest Region
Analyzes the environmental effects for
decommissioning approximately 84 miles of road across the Forest. Road decommissioning
activities are proposed to improve hydrologic function and aquatic habitat in several high priority
sixth-field subwatersheds. This EA analyzes three alternatives.
100 pp. Tables, figures, charts, maps, references, appendices, illus. Priority areas for watershed and aquatic habitat restoration are within the Fifteenmile
Creek, Hood River, and Sandy River basins. Captured March 5, 2009.
2008-01-01T00:00:00Z