  • United States. Bureau of Land Management. Prineville District (2008-01-18)
    Approves plan renewing the grazing lease for ten years with no changes in terms and conditions.
  • United States. Bureau of Land Management. Roseburg District Office (2008-07-07)
    Announces decision to authorize implementation of the Proposed Action Alternative as described in the Rone Access Environmental Assessment. The Rone Access will be a 40 foot road, taking off of the 24-3-30.0 road. Construction ...
  • United States. Bureau of Land Management. Roseburg District Office (2008-03-07)
    Proposes to grant Roseburg Resources Company's request for a three-year road-use permit and to authorize the construction of approximately 40 feet of new road clearing approximately 40 feet (.8 acres) of a 22-year old, ...
  • United States. Bureau of Land Management. Roseburg District Office (2008-05-14)
    Determines no environmental impact statement is needed for project constructing a 40 foot road, beginning at the 24-3-30.0 road. This project is within the General Forest Management Area Land Use Allocation and will cross ...
  • Sisters Ranger District (Or.) (2006-08-10)
    Announces decision to approve the master plan for the reconstruction of Round Lake Christian Camp following the destruction of the August 2003 B&B Complex Fire. Includes rebuilding cabins, shower, bath facilities and ...
  • United States. Bureau of Land Management. Lakeview District (2007-05-31)
    Categorically excludes project removing encroaching western juniper from some 1600 acres of 3400-acre area in which sage grouse will shortly be reintroduced. Includes cutting juniper by chainsaw or other manual methods, ...
  • United States. Bureau of Land Management. Eugene District (2006-07-17)
    Announces decision to issue a right-of-way grant of approximately .15 acres to Lane County for the facilitation of replacing Row River Bridge.
  • Willamette National Forest (Agency : U.S.) (2004-10)
    After performing a preliminary assessment using a Niton XRF unit on waste rock dumps at the Ruth Mine, 8 miles northeast of Elkhorn, a site inspection was recommended because of the concentration of various elements, the ...
  • Willamette National Forest (Agency : U.S.); United States. Forest Service. Pacific Northwest Region (2005-02-23)
    Documents decision to initiate a CERCLA (Comprehensive Environmental Response Compensation and Liability Act) process after an abbreviated preliminary assessment found release of hazardous elements within the Ruth Mine #1 ...
  • Bend-Fort Rock Ranger District (Or.) (2008-03-25)
    Announces decision to improve habitat conditions on approximately 95 acres of existing upland meadow, aspen and willow habitats in the Ryan Ranch Meadow area west of the Deschutes River by broadcast burning approximately ...
  • Bend-Fort Rock Ranger District (Or.) (2007-10-25)
    Announces decision to improve habitat conditions on approximately 95 acres of existing upland meadow, aspen and willow habitats in the Ryan Ranch meadow area west of the Deschutes River by broadcast burning approximately ...
  • United States. Bureau of Land Management. Roseburg District Office (2008-01-28)
    Determines no environmental impact statement is needed for project occurring on two units (approximately 200 acres) of 33 to 64 year-old second-growth forest located in the Elk Creek/Upper Umpqua Fifth-Field Watershed. ...
  • United States. Bureau of Land Management. Roseburg District Office (2007-08-21)
    Determines no environmental impact statement is needed for project occurring on two units (approximately 200 acres) of 33 to 64 year-old second-growth forest located in the Elk Creek/Upper Umpqua Fifth-Field Watershed. ...
  • United States. Bureau of Land Management. Roseburg District Office (2007-08-15)
    Announces decision to authorize the implementation of the Proposed Action Alternative. The proposed commercial thinning and density management will occur on two units (approximately 200 acres) of 33 to 64 year-old second-growth ...
  • United States. Bureau of Land Management. Roseburg District Office (2007-06-21)
    Proposes commercial thinning and density management on two units (approximately 206 acres) of mid-seral, second-growth forest located in the Elk Creek Fifth-Field Watershed. Includes removing 11 acres for the development ...
  • United States. Bureau of Land Management. Salem District (2008-05-19)
    Finds no further environmental analysis is needed for project proposing to fall, buck and scale sample trees (sample tree felling) during the 2008 calendar year to ensure the accuracy of timber cruises for future forest ...
  • United States. Bureau of Land Management. Eugene District (2007-08)
    Proposes salvage activities on about 40 acres, removing 650 thousand board feet (MBF) of blow down timber removed via a timber sale.
  • United States. Bureau of Land Management. Vale District (2006-08-07)
    The proposed action would be to remove all of the horses from the Sand Springs HMA in the fall of 2006 for a period of two growing seasons. The proposed action would include eventual return of all freeze branded fertility ...
  • United States. Bureau of Land Management. Vale District (2006-08-23)
    Finds no further environmental study is needed for project removing all of the horses from the Sand Springs HMA in the fall of 2006 for a period of two growing seasons. The proposed action would include eventual return of ...
  • United States. Bureau of Land Management. Salem District (2008-08)
    EA analyzes three alternatives outlining integrated management scenarios, and the no action alternative which describes current management actions. Predominant actions include developing recreation opportunities (e.g. ...