dc.description |
13 pp. References, map, appendices. Section 33 and 34, T.23S, R.4W; and Section 3, T.24S, R.4W; W.M. Captured July 26, 2007. |
en |
dc.description.abstract |
Proposes to replace four stream crossings in the Elk Creek fifth-field watershed by excavating the fill material from around the old culvert, removing the culvert, and replacing it with a round pipe or bottomless pipe on concrete footing. The new culvert would be placed in the stream channel and compacted fill material placed around the sides and top. |
en |
dc.language.iso |
en_US |
en |
dc.relation.ispartofseries |
NEPA; |
|
dc.subject |
Culverts -- Oregon -- Roseburg Region |
en |
dc.subject |
Public lands -- Oregon -- Roseburg Region |
en |
dc.title |
Elk Creek stream crossing upgrade project environmental assessment |
en |
dc.title.alternative |
Environmental assessment: Elk Creek stream crossing upgrade project |
en |
dc.type |
Other |
en |